The overall total does not reach 100% at the moment, allowing for some flexibility for future unexpected categories. | The overall total does not reach 100% at the moment, allowing for some flexibility for future unexpected categories. | ||
+ | |||
+ | == Project Plan == | ||
+ | {{Main| /Plan | l1= Project Plan}} | ||
+ | The project plan must be documented on the project schedule page([[RBE10K/Schedule]]), and summarised on the section ''"Project schedule and timeframe"'' of the main project wiki page ([[RBE10K#Project_schedule_and_timeframe|RBE10K]]). Currently, the project schedule has a very preliminary plan, schedule and design. The following is a summary of the new comprehensive plan, detailed in the main section above. The project plan as proposed initially by George (through Primavera Systems) consists of the following phases: | ||
+ | * Pre-settlement: | ||
+ | ** Mission and vision | ||
+ | ** Project charter | ||
+ | ** Project location | ||
+ | ** Domestic government requirements | ||
+ | ** International requirements | ||
+ | ** Media and Communications | ||
+ | ** Human Resource management | ||
+ | ** Project Design philosophy | ||
+ | ** Front-end engineering design | ||
+ | ** Detailed engineering and systems design | ||
+ | ** Various experiment result criteria | ||
+ | ** Budgeting | ||
+ | ** Fund raising | ||
+ | ** Independent fund management | ||
+ | ** Mobilisation and site surveys | ||
+ | ** Procurement of initial equipment/materials | ||
+ | ** Construction of staging ground | ||
+ | * Post-settlement: | ||
+ | ** Site mobilisation of Alpha Team | ||
+ | ** Procurement for Camp Alpha | ||
+ | ** Construction of Camp Alpha | ||
+ | ** Final mobilisation | ||
+ | ** Procurement for main city | ||
+ | ** Construction of main city systems | ||
+ | ** Project monitoring | ||
+ | ** Project feedback and control systems | ||
+ | ** Project financial audit | ||
+ | ** Project resource audit | ||
+ | ** Project deliverables | ||
+ | ** Project Close-Out report | ||
+ | ** Demobilisation or remobilisation | ||
== Members == | == Members == |
Revision as of 19:56, 29 April 2013
<data table="RBE10K_Teams" template="Infobox RBE10K_Teams"> Coordinators= User:Ziggy & User:Leandro Activities=Define objectives on newly created teams, as per project requirements </data>
This is the Wiki page for The RBE10K Project's Projection Team. See the list of all Teams.
Contents |
Objectives
Allocate budgeting and define, according to the needs of the project, the objectives and milestones for each RBE10K Team.
Budgeting
The current proposal for the overall budget is $100 million US dollars. The budget will be distributed in percentages for a number of purposes, described below as a preliminary allocation, without real knowledge of reasonable costs incurred per area:
- 10% of the budget for public buildings
- If Central Dome: 10 x $1 million Earhships (excluding furniture, equipment, decoration, etc)
- 10-15% for private housing
- If Capsule Earthships: 5 x $2 million Earthships including capsules 2,000 capsules and bedding each, lounge, kitchen, eatery, furniture, toilets and showers
- 10% for sustainable energy production
- 5-8% for food (for use until the community can be self-sufficient for producing its own food)
- At 2000 calorie requirement for each person per day
- 10,000 people, for 365x2 days = 2000 x 10,000 x 730 = 14,600,000,000 calories in total
- One kg of dry grain contains approximately 3000 calories
- Total number of grain required = 14,600,000,000 / 3000 kg = 4866 tonnes => round to 5,000 tonnes
- The FOB price per tonne of typical grain like lentils is $1,000 per tonne, i.e. $5 million overall (5% of the budget for food)
- Food would also require the purchasing of silos, or materials to build them.
- 5-10% for furniture
- 10-15% for machinery
- 10% for computer and medical equipment
- 5-10% for Internet service
- 5% for materials for clothing, cooking, exercising and other miscellaneous
The overall total does not reach 100% at the moment, allowing for some flexibility for future unexpected categories.
Project Plan
|{{#if:|, | and }}[[{{{2}}}|{{{2}}}]]}}{{#if: |{{#if:|, |, and }}[[{{{3}}}|{{{3}}}]]}}{{#if: |{{#if:|, |, and }}[[{{{4}}}|{{{4}}}]]}}{{#if: |{{#if:|, |, and }}[[{{{5}}}|{{{5}}}]]}}{{#if: |{{#if:|, |, and }}[[{{{6}}}|{{{6}}}]]}}{{#if: |{{#if:|, |, and }}[[{{{7}}}|{{{7}}}]]}}{{#if: |{{#if:|, |, and }}[[{{{8}}}|{{{8}}}]]}}{{#if: |{{#if:|, |, and }}[[{{{9}}}|{{{9}}}]]}}{{#if:|, and [[{{{10}}}|{{{10}}}]]}}{{#if: | (too many parameters in {{main}})}}
The project plan must be documented on the project schedule page(RBE10K/Schedule), and summarised on the section "Project schedule and timeframe" of the main project wiki page (RBE10K). Currently, the project schedule has a very preliminary plan, schedule and design. The following is a summary of the new comprehensive plan, detailed in the main section above. The project plan as proposed initially by George (through Primavera Systems) consists of the following phases:
- Pre-settlement:
- Mission and vision
- Project charter
- Project location
- Domestic government requirements
- International requirements
- Media and Communications
- Human Resource management
- Project Design philosophy
- Front-end engineering design
- Detailed engineering and systems design
- Various experiment result criteria
- Budgeting
- Fund raising
- Independent fund management
- Mobilisation and site surveys
- Procurement of initial equipment/materials
- Construction of staging ground
- Post-settlement:
- Site mobilisation of Alpha Team
- Procurement for Camp Alpha
- Construction of Camp Alpha
- Final mobilisation
- Procurement for main city
- Construction of main city systems
- Project monitoring
- Project feedback and control systems
- Project financial audit
- Project resource audit
- Project deliverables
- Project Close-Out report
- Demobilisation or remobilisation
Members
{{#css:Template:RBE10K TableRows/css}}{{#css:
.col1 {width:{{#if:|{{#explode:{{{widths}}}| |0}}|{{#switch:{{#ifeq: x | | 0 | {{#ifeq: x | | 1 | {{#ifeq: Activities | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|2=20|3=15|4=12|5=10}}}}%; } .col2 {width:{{#if:|{{#explode:{{{widths}}}| |1}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: Activities | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|2=80|3={{#if:|70|15}}|4=12|5=10}}}}%; } .col3 {width:{{#if:|{{#explode:{{{widths}}}| |2}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: x | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|3=70|4={{#if:|64|12}}|5=10}}}}%; } .col4 {width:{{#if:|{{#explode:{{{widths}}}| |3}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: x | | 2 | {{#ifeq: x | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|4=64|5=10}}}}%; } .col5 {width:{{#if:|{{#explode:{{{widths}}}| |4}}|60}}%; } .col6 {width:{{#explode:{{{widths}}}| |5}}%; } .col7 {width:{{#explode:{{{widths}}}| |6}}%; } .col8 {width:{{#explode:{{{widths}}}| |7}}%; } .col9 {width:{{#explode:{{{widths}}}| |8}}%; }
}}{{#wdbq: RBE10K_Team_Members | criteria = _SourceArticle=:Projection | sort = Name |{!RBE10K_TableRows ! {$Name} ! {$User!N/A} ! {$Activities} !} |
}}
<data table="RBE10K_Team_Members">
Name=Leandro
User=User:Leandro
Activities=Project visionaire and organiser
</data>
<data table="RBE10K_Team_Members"> Name=Boris User=User:BuckMinsterFuller Activities=Project visionaire and organiser </data>
<data table="RBE10K_Team_Members"> Name=George User=User:Anijahobi Activities=Project manager, visionaire and organiser </data>
<data table="RBE10K_Team_Members"> Name=Ziggy User=User:Ziggy Activities=Project visionaire and organiser </data>
Requests
{{#css:Template:RBE10K TableRows/css}}{{#css:
.colteam_requests1 {width:{{#if:30 15 55|{{#explode:30 15 55| |0}}|{{#switch:{{#ifeq: x | | 0 | {{#ifeq: x | | 1 | {{#ifeq: Description | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|2=20|3=15|4=12|5=10}}}}%; } .colteam_requests2 {width:{{#if:30 15 55|{{#explode:30 15 55| |1}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: Description | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|2=80|3={{#if:|70|15}}|4=12|5=10}}}}%; } .colteam_requests3 {width:{{#if:30 15 55|{{#explode:30 15 55| |2}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: x | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|3=70|4={{#if:|64|12}}|5=10}}}}%; } .colteam_requests4 {width:{{#if:30 15 55|{{#explode:30 15 55| |3}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: x | | 2 | {{#ifeq: x | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|4=64|5=10}}}}%; } .colteam_requests5 {width:{{#if:30 15 55|{{#explode:30 15 55| |4}}|60}}%; } .colteam_requests6 {width:{{#explode:30 15 55| |5}}%; } .colteam_requests7 {width:{{#explode:30 15 55| |6}}%; } .colteam_requests8 {width:{{#explode:30 15 55| |7}}%; } .colteam_requests9 {width:{{#explode:30 15 55| |8}}%; }
}}{{#wdbq: RBE10K_Team_Requests | criteria = _SourceArticle=:Projection | sort = Name |{!RBE10K_TableRows ! widths=30 15 55! {$Name} ! {$Ref!N/A} ! {$Description} !} |
}}
<data table="RBE10K_Team_Requests">
Name=We need people with commerce or accountancy knowledge, and project planners
Ref=User:Ziggy
Description=We need people with commerce or accountancy knowledge, and project planners
</data>
Offers
{{#css:Template:RBE10K TableRows/css}}{{#css:
.colteam_offers1 {width:{{#if:30 15 55|{{#explode:30 15 55| |0}}|{{#switch:{{#ifeq: x | | 0 | {{#ifeq: x | | 1 | {{#ifeq: Description | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|2=20|3=15|4=12|5=10}}}}%; } .colteam_offers2 {width:{{#if:30 15 55|{{#explode:30 15 55| |1}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: Description | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|2=80|3={{#if:|70|15}}|4=12|5=10}}}}%; } .colteam_offers3 {width:{{#if:30 15 55|{{#explode:30 15 55| |2}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: x | | 2 | {{#ifeq: | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|3=70|4={{#if:|64|12}}|5=10}}}}%; } .colteam_offers4 {width:{{#if:30 15 55|{{#explode:30 15 55| |3}}|{{#switch:{{#ifeq: x | | 0 |
{{#ifeq: x | | 1 | {{#ifeq: x | | 2 | {{#ifeq: x | | 3 | {{#ifeq: | | 4 | {{#ifeq: | | 5 | {{#ifeq: | | 6 | {{#ifeq: | | 7 | {{#ifeq: | | 8 | 9 }} }} }} }} }} }} }} }}
}}|4=64|5=10}}}}%; } .colteam_offers5 {width:{{#if:30 15 55|{{#explode:30 15 55| |4}}|60}}%; } .colteam_offers6 {width:{{#explode:30 15 55| |5}}%; } .colteam_offers7 {width:{{#explode:30 15 55| |6}}%; } .colteam_offers8 {width:{{#explode:30 15 55| |7}}%; } .colteam_offers9 {width:{{#explode:30 15 55| |8}}%; }
}}{{#wdbq: RBE10K_Team_Offers | criteria = _SourceArticle=:Projection | sort = Name |{!RBE10K_TableRows ! widths=30 15 55 ! {$Name} ! {$Ref!N/A} ! {$Description} !} |
}}
<data table="RBE10K_Team_Offers">
Name=We can organise a template with a structure and clear objectives for any newly created team
Ref=User:Ziggy
Description=Whenever creating a new team, please rely on us to set the team up. We may need to have a conversation about the objectives of the team, but we'll ensure those objectives are aligned with the needs of the project
</data>